  AIP
SUP

AIP SUP 08/26
11 FEB 2026
 
     
   

                                             OEJN — JEDDAH / KING ABDULAZIZ INTL AIRPORT

Replacing North Jetway and Introducing temporary new aircraft stand Project to Operate the South Jetway

1 .Introduction:

The purpose of this AIP Supplement is to notify aircraft operators regarding the new project of replacing the current north jetway on Apron 8 and introducing a new aircraft stand (Stand: R5) on Apron 8 at King Abdulaziz Intl Airport (KAIA) to operate the south jetway during the project of replacement of the north
jetway at apron 8.

2 Timeframe for the installation activities:

The period of the installation activities of replacing the current north jetway on Apron 8 and introducing a new aircraft stand (Name: R5) on Apron 8 to operate the south jetway. These activities are divided as follows:
Project
Phases
Activity Duration Consequence Remark
Phase 1 Installation new
marking for the
temporary parking
stand R5 and Removal
of temporary aircraft
leading line R4
+ 8 months
  • R2 is closed by SUP
  • R1 will be only closed during the start of phase 2
  • Docking to stand R5 will be via follow me and marshaling and R5 will remain active until the end of the project.

-

 
Phase 2 Civil Work and removal
of current jetway
+ 4 weeks
Phase 3 Civil Work for
preparation for the
installation of the new
jetway
+ 4 weeks
Phase 4 Civil Work for
installation of the new
jetway
+ 4 weeks
Phase 5 Test commissioning + 8 weeks

3 Areas affected during the work in progress:

 
Working Area
Points  Coordinates Height above ground
level
Elevation above
mean sea level
Equipment
1 21°40'20.87"N 39°08'06.51"E 20m 29m Crane within the fence
area
2 21°40'22.81"N 39°08'05.77"E 20m 29m Crane within the fence
area
3 21°40'23.52"N 39°08'05.61"E 20m 29m Crane within the fence
area
4 21°40'24.89"N 39°08'04.92"E 20m 29m Crane within the fence
area

The attached illustration shows the areas affected during work in progress

4 Activation of the AIP supplement:

NOTAM will be issued to active the phases. 

5 Replacement or cancellation of the AIP SUP:

Any significant change in the current information would be notified by replacement AIP.

This AIP Supplement will remain effective until further notice, and NOTAM will be issued to announce the cancellation of this AIP SUP.

6 Inquiries:

For any inquiries, please contact:
Aerodrome / SANS CONTACT DETAILS
Jeddah TWR Name: JED Tower
Email: jedtwr@sans.com.sa
Aerodrome Operator (JEDCO) Name: Adil Abdo
Email: aabdo@jeddahairports.sa
Aerodrome Operator (JEDCO) Name: Moataz Faraj
Email: mafaraj@jeddahairports.sa

AIP SUP 45/25 hereby replaced. 